banner image

“Square peg, triangular hole,” is how Cartwright Pickard director Ian Walsh describes the design challenge at Kellstone, a new grade A office development in Leeds

The building occupies a triangular plot at the north-eastern gateway of Aire Park in the city centre, a mixed-use district taking shape on the former site of the Tetley Brewery. Unusually, it was always going to be precast concrete: almost the entire building, from the ground-floor beams and columns to the brick facade panels, to the hollowcore floorplanks, the core, stairs and even non-structural walls, was manufactured off site by Inhus, a long-term supply chain partner of Aire Park’s developer, Vastint.

On the one hand, this meant that the practice could tailor the architecture to the right construction method, rather than having to shoehorn it in later. On the other, Walsh points out, they faced the unavoidable challenge of reconciling two different geometries: “From the outset, we had a fixed plot parameter and a fixed orthogonal system.”  

Cartwright Pickard’s competition-winning design didn’t immediately seem suited to a modular solution. Even though the seven-storey building’s richly detailed main elevations involve high levels of repetition, the problem was the triangular form, which tapers to a distinctive prow at the western end. But working with Inhus, they found a way to realise this bull-nosed curve within the constraints of the system, refining it to five repeating panels.

Inhus then built a one-to-one scale panel in its factory in Lithuania to show the architects how it would work in practice. “We saw how they were able to control both the batching of the bricks and the quality of the concrete,” explains Cartwright Pickard associate Ahmad Mohammed. “The bricks themselves are not curved, they’re faceted, but it works well. They were able to achieve a great enough curve on the overall panel, without the need for brick specials.”

The panelised system came into its own for the main facades, which were designed for maximum efficiency. Two-thirds of the building envelope is made from the same repeated base panel, one storey high and 5.4m wide, with two window openings. Each comprises a concrete outer leaf with brickwork cast in, an insulation layer and a load-bearing inner leaf of exposed concrete. The outer leaf combines light buff and glazed green brickwork – a nod to the Victorian-era pubs long sustained by the brewery – and fluted pale concrete fins. The vertical joints are hidden within the fins, while the horizontal lines are articulated with a double soldier course of bricks. 

Aside from the prow, there are three main areas of variation, at the top and bottom of the building, and the main entrance. The 1.5-storey ground floor, containing shops and restaurants, was constructed from precast beams and columns, with glazed brick infills. The sculpted panels that wrap around the top floor had to be cast in single-window units – they are 5.4m tall so needed to be narrower to fit the truck-bed dimensions. A pigment was added to control the pale tone of the concrete. “One of our early concerns was that when you have exposed precast panels next to one another, you can get 10 shades of grey – it doesn’t read quite right. Inhus were very good at saying, ‘we know what you want the end product to look like, this is how you achieve that consistency’.” 

Steel moulds were used to ensure the detailing was as sharp as possible. “They are all chamfered and curved, which creates a lovely play of light and shadow along the top of the building,” says Mohammed. To get the tone right, Inhus sent over a number of 600mm x 600mm swatches for the architects to consider. 

In the centre of the front elevation, the rhythm of the facade changes to an 8.1m-wide bay, expressed in light precast concrete panels for the full height of the building. Closer to the entrance, a pattern of repeating circles begins to emerge in the concrete. This was created by using a surface retarder to selectively expose the aggregate just below the surface. “It’s an abstraction of beer bottles and barrels on their sides,” says Walsh. “We were able to use the precast technology to give a narrative link back to the brewery.”

Inside, the office spaces are column-free, with hollowcore planks spanning up to 16m from either the main core or a smaller stair core near the prow to the perimeter walls. The soffits have been left exposed with services suspended underneath. There are few additional linings or finishes: the inner face of the sandwich panels has a light plaster skim and the core walls and other non-structural partitions are all left exposed, with light panels and other fittings cast in. 

Even though these elements were manufactured in a different country, the architects were able to closely monitor these visual elements. “Inhus 3D-modelled everything to the nth degree,” says Walsh, “which meant we had quality control over connections, joints and finishes, as well as the fire and acoustic quality of the system.”

Each floor was built and made watertight in just two weeks. After the beam and column arrangement on the ground floor, each level followed the same process: hollowcore planks, then core walls, then perimeter panels, which were connected to the planks via starter bars and permanently grouted through cast-in tubes. “There were only six or so operatives on site,” says Walsh. “It was the quietest, cleanest site we’ve ever been on.”

Kellstone is now complete, and Vastint hopes that its ground-floor shops and restaurants will soon be busy with people spilling into the public realm. The building forms a V-shaped square with Tetley’s art deco former headquarters – a characterful survivor from a landscape once dominated by factories and warehouses. The 24-acre Aire Park promises a very different future – although, with Kellstone at its heart, it will be one still shaped and defined by manufacturing processes.

Project Team

Architect 

Cartwright Pickard

Structural engineer 

Curtins

Precast designer and supplier 

Inhus

Main contractor 

Moortown

Photos 

Mark Newton Photography