The Madrid Windsor Tower Building Fire, 14-15 February
2005
Save this page as a pdf
Landmark 29-floor tower on Madrid skyline remained standing
despite a 26-hour, multiple-floor fire.
Despite a complete burn-out, the strength provided by a
technical concrete floor, plus the passive fire resistance of the
building's concrete core and frame, prevented the building from
collapse.
The only part of the building to collapse was the network of
steel perimeter columns supporting the slab on the upper
floors.
The building was in the process of refurbishment and
fireproofing to modern standards when the fire occurred; some
fireproofing was being provided on the steel perimeter columns.
NIST's interim report on the World Trade Center disaster
recommends the inclusion of 'strong points' within the building
frame design - the Madrid Windsor Building's strong points were its
two concrete 'technical' floors and the concrete core system
enabling the building to survive complete burnout.
This case study is an example of the excellent performance of a
concrete frame designed using traditional methods and subjected to
an intense fire. It also highlights the risks when active fire
protection measures fail or are not included in steel frame
construction.
The Madrid Windsor Building is situated in the heart of the
Spanish capital's financial district and was a distinct and
familiar landmark on the city's skyline. Built between 1974 and
1978 by architects Alas Casariego, its occupants included high
profile corporate clients including accountants Deloitte and
Spanish legal firm Garrigues.
The building totalled 32 storeys, with 29 floors above ground
and three below. A concrete core and concrete frame supported the
first 16 floors. Above that was a central support system of
concrete columns, supporting concrete floors with steel perimeter
columns. An additional feature was the presence of two 'technical
floors' - concrete floors designed to give the building more
strength. One was just above the ground level and the other at the
17th floor.
The tower was built using normal strength concrete and before
modern fire proofing standards, without any sprinkler system. It
was undergoing a complete refurbishment, including the installation
of various active fire prevention and resistance measures, when the
fire began at around 11pm on 14 February 2005. Fortunately the
building was empty of people at the time.
The fire started on the 21st floor and quickly spread both above
and below. Upward spread was by means of internal openings made as
a result of the refurbishment and the failure of fire stops between
the perimeter column and steel/glass façade. Downward spread is
thought to have been caused by burning façade debris falling
through windows on lower floors.
Because of the height of the structure and the extent of the
blaze, firefighters could only mount a containment operation and
ensure that neighbouring buildings were protected. The fire
eventually finished 26 hours later, leaving a complete burn-out
above the fifth floor. The steel-glass façade was completely
destroyed, exposing the concrete perimeter columns. The steel
columns above the 17th floor suffered complete collapse, partially
coming to rest on the upper technical floor. The insurance value of
the total damage caused was €122 million.
Crucially, the building remained standing despite the intensity
of the fire. An investigation is underway between Spanish technical
agency Intemac and UK authorities including Arup Fire, the
University of Edinburgh and the concrete industry including
Cembureau, BCA and The Concrete Centre. Preliminary findings
suggest that a combination of the upper technical floor and the
excellent passive fire resistance of the tower's concrete columns
and core prevented total building collapse.
The fire is significant in terms of its potential similarities
between the collapse of the building's steel frame above the 17th
floor and the experience seen at the World Trade Center. Notably,
one of the recommendations of NIST's interim report on the World
Trade Center disaster is for tall building design to incorporate
'strong points' within the frame.
This case study is an example of the excellent performance of a
concrete frame designed using traditional methods and subjected to
an intense fire. It also highlights the risks when active fire
protection measures fail or are not included in steel frame
construction.