The Shard

Save this page as a pdf

The Shard river shot 
  The Shard internal shot     

Images: courtesy of Sellar Group

The Shard will be the UK’s tallest building. It forms part of the £2 billion Renzo Piano designed London Bridge Quarter regeneration project near London Bridge and has been so named because of its slender, spire-like shape covered with facets of angled glazing that are intended to reflect light and the changing patterns of the sky.

An innovative approach was taken to enhance the construction programme and reduce programme risk. This involved ‘jump-starting’ the concrete core and steel structure to allow construction above and below ground to start simultaneously. Such an approach would have been challenging enough without taking into account the constrained urban site and having to operate amongst the thousands of commuters using London Bridge station every day. In addition, the approach has never been used on a project of this size before.

The initial plan was to construct a cofferdam at the centre of the site and excavate so that work could start on the core from base-up. Meanwhile, top-down construction would be used for the area between the cofferdam and the perimeter secant piled wall. However, jump-starting meant that work could start on the core and steelwork whilst the core continued to be built downwards into the basement. Jump-starting would also remove the need for installing the cofferdam and had the potential to reduce the duration of the construction programme by three months.

The 250m high core is being slip-formed and was started at basement level B2, 9m above the lowest excavation level. This was achieved by sinking large steel box columns into support piles directly beneath the core, and constructing a grillage of reinforced concrete beams at B2 level, connected to the piles with welded couplers. This takes the load as the core is constructed skywards. The basement below has now been excavated and the large raft foundation poured. The 6m-high reinforced concrete core walls from level B3, the lowest level, to B2 have been constructed using self-compacting concrete pumped from the bottom of the form so that a tight fit is achieved between the walls and the grillage of beams.

The concrete for the slip-formed core is grade C50/60 concrete achieving 30 MPa cube strength at 24 hours. There are 36 different concrete mix types to allow for variations in weather, time of year, height of pumping etc. The slip-form rig also holds one of the cranes for the construction so that the crane is moved up the building with the core. This has added an extra 180 tonnes to the weight of the rig which has an area of 26m x 22m. The core itself covers an area of 22m x 19m. The slip-forming was started in January 2010 and 72 storeys of slip-forming should be complete at the end of the year. The maximum speed that the slip-forming has achieved is 3.6m in 24 hours.

The core had already reached 21 storeys high by the time that 700 truckloads of concrete were poured into the basement to form the 3m deep raft foundation upon which the tower will sit. Carried out over 36 hours, the 5,500m3 single concrete pour is one of the largest ever undertaken in the UK. At the peak of the pour, trucks were arriving on site every two minutes. Three concrete pumps were installed to pump up to 150m3 an hour to ensure a fast truck turnaround time. The concrete was poured in layers 750mm deep. This helped to reduce heat build-up and regulated the concrete placement. Reducing heat was important in order to limit the potential for high levels of shrinkage and cracking. The C35/45 concrete contains a cement blend using 70 per cent ground granulated blast-furnace slag (ggbs) to limit early heat gain. This high level of cement replacement has the potential disadvantage of low early strength gain. This was overcome by developing the concrete mix so that it would achieve sufficient strength gain to meet initial structural requirements within 14 days with the full strength being achieved at 56 days.

Levels 40 to 72 are to be constructed in post-tensioned concrete on high strength (C65/80) concrete columns, but these levels have not yet been started. Pumping concrete up 250m is just another of the challenges this project has posed for the concrete subcontractor to overcome.

Project team

Client: Sellar Properties
Architect: Renzo Piano Building Workshop/Adamson Associates
Engineer: WSP Cantor Seinuk
Contractor: Mace
Concrete subcontractor: Byrne Bros

My Centre

Gain access to all the free services available on this website

Login

Don't have an account?

Register here

Related Information

 

Publications icon Publications

 

Concrete Structures 10