Brewery Wharf, Leeds
Save this page as a pdf
As work draws to a close on the third and final stage of the
three-year, £60 million Brewery Wharf apartment development, built
on a brownfield site in Leeds city centre, Paul Russell
examines the challenges overcome to realise this latest
monument to contemporary urban living.
The challenges
Architects and engineers will be familiar with working on
tight, pinned in sites. Indeed, there may be more extreme
situations than the one faced by the designers of Brewery
Wharf. But try it out for size: a 9,600 sq m site, bordered
on one side by a busy road and bridge, on another by a river and on
the third by a neighbouring hotel construction site. You're
building on water retentive gravel and the plans demand a car park
basement covering the whole footprint. Planning consent
places a rigourous cap on building height and an acoustic
performance that exceeds the new Part E regulations.
This was the challenge confronting Robinson Design Group when
awarded the job by Totty Construction of designing and building 326
apartments across five buildings on the banks of the River Aire in
Leeds. Taking its name from the nearby Tetley's site, Brewery
Wharf was scheduled in three phases over 38 months. The only
way to embark on such a large-scale project was to break it down
into individual elements to identify the most cost-efficient
construction methods. Simplicity and buildability were the
emphasis throughout the process.
The solution
Brewery Wharf's ultimate client, Barratt Leeds, automatically
specify the use of concrete over steel in their apartment
developments for two main reasons one to achieve the maximum
ceiling height and avoid cluttering internal spaces with intrusive
bulkheads and beams, and the other related to concrete's acoustic
properties. So Robinsons knew the material they had to work
with what remained to be decided was the exact specifications to
meet the constraints posed by the site.
The development's location beside the River Aire meant building
on porous open textured gravel with a great deal of water
retention. Water levels could rise at any time. Into
this an underground car park had to be built, covering the entire
site. Brian Smith, Robinson's Design Director, decided a
water-resistant structure using a standard C40 blended mix would do
the job, without the need for water-proofing membranes or
admixtures. Smith says he is not a 'great believer' in the
use of admixtures, primarily because they don't stop the concrete
from shrinking as it cures.
David Begg, project manager at David Ashley, the concrete
sub-contractor on the project, agrees, adding "the problem with
admixtures is that they need a plasticizer, which means that the
concrete takes longer to reach its strength. We were
achieving 28 Newtons within three days at Brewery Wharf, which I
think is pretty good." Reinforcement was specified at 100mm
centres instead of a more typical 200mm in the basement slab and
walls, to prevent cracking and additionally help guarantee a
water-proof structure. Finally the basement slab laid over
the pile caps was designed to resist uplift forces from water.
For the structure above ground level, Smith's analysis of
requirements led him to a 225mm RC flat slab solution. The
attractiveness of this approach was in the ability to keep floor
heights down and realise the clean lines needed in the
apartments. The design enabled a 2975mm floor to floor height
and a continuous soffit in apartment ceilings, uninterrupted by
unsightly downstands.
Construction
One unforeseen element in the initial design, and of which
Smith is particularly pleased with the outcome, was the need to
incorporate an element of rigid frame action into the
project. The planning-approved blueprint presented a
restricted opportunity to incorporate sheer walls and shafts.
Working closely with contractor Totty Construction, Smith responded
with a design that increased column width while still being
comfortably accommodated within the flat layout.
Smith comments "We did some very interesting and useful work
in the process of resolving this lateral strength issue. It's
broken new ground for us in terms of medium-rise projects and I'm
looking forward to applying this approach elsewhere."
The flexibility of the concrete solution also came into play
when designing a concrete transfer structure to facilitate clear
driveways in Brewery Wharf's basement car park.
Superstructure columns needed to be diverted via a series of 850mm
transfer beams to columns in the basement. Standing under one
of these beams beneath the tallest block, St. James Quay, it's
impressive to think that nine storeys of vertical weight is being
diverted 2.5 metres sideways before reaching the foundations.
Another point of interest was the decision to replace steel
construction for the roof-top penthouse apartments with concrete
after Phase 1. It was felt that concrete was more
architecturally compatible with the scheme overall besides the fact
that life was simplified with one less contractor on-site.
And, in acknowledgement of the confined nature of the site, it was
decided to keep the use of rebar down to the moderate level of
typically 3% or less by weight of cross sectional areas for columns
and 130 kg/m3 for floor slabs. Not only did this
mean less reinforcement being stored on the site, but it also made
the concrete easier to cast, leading to a high-quality end
result.
Of course, the new occupants of Brewery Wharf may relish all
the brashness and excitement of city centre living, but don't want
to hear noise when they are at home. Barratts set demanding
acoustic requirements for the project of a maximum of 34-35Db for
external walls and windows and 53Db airborne level difference for
internal/party walls. Blockwork walls and a floor acoustic
screed help achieve these targets, but the main contributor to
quiet urban living is ultimate sound barrier provided by the flat
slab and concrete frame construction.
The third and final phase of the development, containing 98
apartments, is due for completion by mid-August 2005, bringing this
£60 million project to a close. Now that the external works
are complete and the scaffolding is down the aesthetics of Brewery
Wharf can clearly be seen a contemporary 'warehouse/industrial'
feel through the use of a simple palette of materials including
metric brick and terracotta rainscreen panelling.
For the inhabitants, the whole development represents both a
pied à terre and a place to get away from it all, right in the
heart of one of England's biggest, buzziest cities.
Project Team at Brewery Wharf
Client: Barratt Leeds
Contractor: Totty Construction Group
Architect: Robinson Architects
Structural Engineer: Robinson Consulting
Project Manager: Turner & Townsend
Concrete contractor: David Ashley